Board level strategy for outsource agreed June 2006.
• UK plant closure target March 2007.
• Outsource scope – £4.8 million spend, 350 line items.
• Development and implementation plan agreed August 2005 with 3 suppliers.
• Core range (17 families) approved and in full production by July 2006.
• Balance of range developed, approved and in full production by April 2007.
• UK plant ceased production February 2007.
• Cost savings achieved £2.1 million.
• Delivery schedule adherence 88%.